Develop Schedule – Timeline

The below process indicates a generic method for the development of a set of program and project plans.  The timeline to complete this process would be approximately 6-8 weeks.

 

# Title Planning level Description
1 Project Brief Level 1 – Program Plan The Sponsor briefs the Program Manager on the Business Case, Scope and Program Timelines
2 Draft Program Plan Level 1 – Program Plan Program Manager develops a draft plan for discussion with Sponsor and other key Stakeholders.  Critical path activity timelines should be indicated and sub-work stream project managers may be required to provide input (Expert Advice) for critical activities.
3 Program Planning Workshop #1 Level 1 – Program Plan Program management team workshop the draft project plan stepping through plan activities.

Items which should be reviewed during the meeting are; Activity Duration, Start/Finish times, Dependencies, Resource constraints, Risks or Issues

4 Project (Work stream) Planning Level 2 – Project plans Workstream leads develop team plans in alignment with Program plan Work Breakdown Structure and Activity Start/Finish
5 Plan Quality Control Level 2 – Project plans Schedule Manager provides Quality Control reports on Program plans and Project (Work stream) plans
6 Revised Program Plan Level 1 – Program Plan Program Manager updates Program plan with Workshop feedback, Quality Control feedback and additional feedback from Project leads.
7 Program Planning Workshop #2 Level 1 – Program Plan Program Management team workshop project plan confirming alignment of  Project lead plans, Dependencies and updating Risk log
8 Baseline Level 1 – Program Plan Steering Committee approves the Baseline Program plan.